On-going inspections are performed to ascertain the progress of construction, establish an estimated value of work in place, identify changes in construction costs or completion, and verify adequacy of remaining funds to complete the work. Quality of workmanship and adherence to bank approved plans are key factors to be addressed.
Periodic site visits must be conducted to evaluate the progress of work at the project and may be requested with or without a contractor's application for payment or owner/borrower's request for funds. The Inspecting Consultant is expected to participate as PNC's representative at routine, monthly construction draw meetings. Below are guidelines for standard requirements of progress reports.
General Information
Owner/Borrower Name
Project name and location
Description of the project
Contractor's AIA requisition number and period covered
Standard Scope of Review
Each report should include commentary on the following topics:
Date of inspection and who attended (include time of day and weather conditions). If visit did not coincide with monthly draw meeting, provide an explanation.
Status of Progress Schedule and Inspector's Estimated Completion Date with commentary on Developer's Project/Draw Status Report.
Discussion of quality of workmanship and materials.
Validation of scheduled values, previous draws, current request and reallocations of scheduled values.
Summary of Change Orders - executed and pending. Include dollar value of changes and commentary on availability of funds in project budget; explain scope of work and impact on original plans and specifications (as to design and quality resulting from change) and on project schedule.
Labor disputes or issues related to trades.
Stored materials inventory and usage (on site and off-site, if requested), including controls, anticipated integration of inventory, protection from elements and damage, etc.
Confirm adherence of work to plans and specifications, noting deviations and impact.
Code compliance or possible violations.
Tenant finish completion: Borrower to provide summary by tenant or trade breakdown for tenant work. Inspector to confirm spaces under construction and progress of each space.
Dollar value of work in place for each draw with explanations of differences between actual costs incurred and requested amounts, if applicable.
Percentage of completion--per line item and overall construction budget.
Adequacy of project funds available to complete project. Indicate if contingency funds are recognized in balancing available funds.
Review retainage. Confirm that retention is consistent with construction documents. Provide opinion on reduction or release of retainage when requested.
Review and comment on laboratory tests and other inspections.
Review and comment on subcontracts and purchase orders, including engagement status and:
conformance to plans and specifications
availability of funds within general contract allowance
submission of lien waivers
Other matters that may arise which would affect the timely completion or quality of work.
Photographs. Comprehensive photographs should be labeled, depicting overall progress of construction at time of site visit, as well as pictures that reflect any areas of concern.
Reporting Requirements:
Questions should be directed to Real Estate Administration.